A group of 18 tunnels totaling 2,665 meters, of which the longest, located up high near the Charabotte waterfall, measures 557 meters.

Eigenschaften

Lage

From Tenay, take the road to Hauteville. On arriving at the plateau, turn left and enter the hamlet of Nantuy. Park. To reach the tunnels, follow the Albarine. Allow 15 minutes of walking.

Karte

Eingänge

Koordinaten und Zugangsbedingungen vor dem Aufbruch immer überprüfen.

  1. Tunnels du Train Fantôme

    45.966284, 5.565956
Alle Eingänge als GPX herunterladen

Beschreibung

Morphologie

The group comprises 18 tunnels totaling 2,665 meters. The longest is located up high, near the Charabotte waterfall, and measures 557 meters.

Geschichte

The project dates from the 1880s; construction was decided in 1900 by the Conseil Général de l'Ain and work began in 1909. The project was contested by many Bugistes who would have preferred a line starting from Ambérieu and serving Brénod and Hauteville.

Work proceeded apace for 1 year (1910), then slowed or stopped at times, to resume properly in 1913, so that by 1914, only 7 to 8 km of track remained to be laid from Hauteville. Indeed, the supply of the worksite and therefore its progress took place via the plateau. In that same year, work stopped again, when the tunnels were almost all bored and only the bridge decks were missing.

However, in 1916, the stored rails were requisitioned by the army. In 1919, the project was relaunched. The last tunnel was then bored. From 1920 to 1932, the boring experienced numerous problems with infiltration and collapse. The trajectories of the galleries had to be modified twice. Three galleries were therefore dug.

The overload of spoil obliged the contractors to buy other land to store the materials. On this occasion, they noticed that not all the land on which the tram was built had been paid for; others, on the other hand, had been paid for twice, and others again had been paid for, but with no use for the worksite.

In 1933, the track was completed and inaugurated by the passage, over part of the section only, of a locomotive and one or two wagons occupied by the local authorities. Subsequently, it was decided to electrify the track and install heavier rails. The old rails were dismantled, but the funding for electrification was never released.

In 1936, the Conseil Général decided to abandon the line and declassify it, which would only take effect in 1951. This track never saw a train carrying passengers and was never used.

Benutzerkommentare (0)

Noch keine Kommentare.

Seien Sie der Erste, der seine Erfahrung teilt!

Registrierte Erkundungen (0)

Noch keine Erkundungen registriert.

Registrieren Sie Ihren Besuch in dieser Höhle!

Enthält Informationen aus Grottocenter (Wikicaves), grottocenter.org, bereitgestellt unter der Open Database License (ODbL 1.0, https://opendatacommons.org/licenses/odbl/1-0/), verändert. · https://grottocenter.org/ui/entrances/5481 · Datenstand 2026 · Quelle: Grottocenter (Association Wikicaves), worldwide collaborative cave database (grottocenter.org), verändert. CC BY-SA 3.0, https://creativecommons.org/licenses/by-sa/3.0/ Grottocenter (Wikicaves) · Text von Vincent (Description sommaire), Vincent, Vincent (Accès depuis Tenay) · bearbeitet von Espeleoworld (normalisiert, übersetzt); die Bearbeitung steht unter der Lizenz CC BY-SA 3.0, https://creativecommons.org/licenses/by-sa/3.0/ · https://grottocenter.org/ui/entrances/5481 · Datenstand 2026 · Die abgeleiteten Daten sind auf Anfrage unter der ODbL erhältlich: [email protected]